Official websites use .mil
Secure .mil websites use HTTPS
April 30, 2019
Kang Border Patrol Headquarters: Construction Generally Met Contract Requirements, but Deficiencies Exist, and the $5.2 Million Project Has Not Been Used or Maintained
SIGAR 19-36-IP —
April 29, 2019
USAID’s Power Transmission Expansion and Connectivity Project: Arghandi-Ghazni Transmission Line Was Generally Built to Contract Requirements, but Four Deficiencies Create Safety Hazards and Could Disrupt Electrical Power
SIGAR 19-35-IP —
April 10, 2019
Schools in Bamyan Province, Afghanistan: Observations From Site Visits at 16 Schools
SIGAR 19-33-SP —
Jan. 30, 2019
Afghan Air Force: DOD Met the Initial Date for Fielding UH-60 Helicopters, but the Program Is at Risk of Not Having Enough Trained Pilots or the Capability to Maintain Future UH-60s
SIGAR 19-18-AR —
Jan. 28, 2019
Marshal Fahim National Defense University: Phase III Construction Generally Met Contract Requirements, but Five Deficiencies and Inadequate Maintenance Increase Safety Risks for Building Occupants
SIGAR 19-16-IP —
Dec. 28, 2018
Afghan National Army Camp Commando Phase III: Facility Construction and Renovation Generally Met Contract Requirements, but Three Construction Deficiencies Increased Safety Risks
SIGAR 19-09-IP —
Dec. 4, 2018
Zarang Border Crossing Point: Facilities Generally Met Contract Requirements, but Construction Deficiencies Pose Safety Concerns
SIGAR 19-07-IP —
Oct. 26, 2018
Afghan National Police Women’s Compound at the Ministry of Interior: Construction Generally Met Requirements, but Use and Maintenance Remain Concerns
SIGAR 19-04-IP —
Oct. 25, 2018
Afghanistan National Defense and Security Forces: DOD Lack Performance Data to Assess, Monitor, and Evaluate Advisors Assigned to the Ministries of Defense and Interior
SIGAR 19-03-AR —
Sept. 20, 2018
Marshal Fahim National Defense University: Phase I Construction Generally Met Contract Requirements, but Non-Compliant Fire Doors and Inadequate Maintenance Place Building Occupants At Risk
SIGAR 18-76-IP —